St Augustines Road, Camden

The project involves the creation of a new 3 storey building with basement to provide 9 new luxury apartments in Camden, North London. There are several constraints to the site including the close proximity of a Network Rail Tunnel and an existing Thames Water Mains that dissects the site. There were also several party wall agreements to resolve.

Webster Charles were appointed as Project managers and Quantity Surveyors to liaise with the statutory bodies to resolve the issues surrounding the development. The works are due to go out to tender at the end of the year with an expected start on site in early 2015. The works are expected to take approximately 12 months.

Programme:
12 Months
Client:
ZEN Developments
Architect:
CZWG
Project Manager:
Webster Charles
Quantity Surveyor:
Webster Charles
Structural Engineer:
Knapp Hicks & Partners
M&E Engineer:
Mower Partnership